Construction along Bridgeport Road, from Gage Road to River Road, is now underway. This segment of the project is currently scheduled for completion in mid-December 2020. Please note that schedules are subject to change based on weather and project requirements. We provide updates to our schedule and the overall project in our Seasonal Project Update, found under Construction Updates.


Listed below is the latest information about ongoing lane closures and traffic detours for the Bridgeport segment:


November 23 – 29 Update

Work in Zone 5 (Great Canadian Way to Hwy 99):


  • To be fully re-opened by end of day Wednesday November 25th.


Work in Zone 3 (No 3 Rd to Great Canadian Way):


  • Bridgeport eastbound lanes closed
  • Bridgeport westbound open
  • Sexsmith southbound from Bridgeport open


Work in Zone 1 (River Rd to No 3 Rd):


  • Bridgeport westbound down to one (1) lane


Traffic mitigation:

  • Electronic signage for B-Port closure reading “Use Sea Island.”
  • Flagging personnel continue to actively direct traffic from high visibility locations
  • Google Maps/Directions are updated to reflect latest traffic patterns


Zones identified as follows:

5 Great Canadian Way to Hwy 99
4 Great Canadian Way Intersection
3 No 3 Rd to Great Canadian Way
2 No 3 Rd Intersection
1 River Rd to No 3 Rd





Questions?